Passengers on the Kelana Jaya LRT line should expect temporary service disruptions between August 9 and November 22, as Prasarana upgrades the line’s Automatic Train Control (ATC) system to the new SelTrac Generation 8.
The new system offers real-time data analytics, enhanced cybersecurity, and more stable communications – part of a long-term solution following the major disruption in November 2022.
Disruption Details
- The works are divided into three phases.
- During Phases 2 and 3, affected stations will open later at 9am (instead of 6am) on weekends and public holidays only.
Phase 1 (Completed)
- Date: Completed on July 19
- Scope: Focused on depot areas (no passenger disruption)
Phase 2 (KLCC to Gombak)
Affected stations:
- KLCC
- Ampang Park
- Damai
- Dato’ Keramat
- Jelatek
- Setiawangsa
- Sri Rampai
- Wangsa Maju
- Taman Melati
- Gombak
Disruption dates (stations open at 9am):
August: 9 (Sat), 10 (Sun), 16 (Sat), 17 (Sun), 23 (Sat)
September: 5 (Fri), 6 (Sat), 7 (Sun), 14 (Sun)
Phase 3 (Lembah Subang to Ampang Park)
Affected stations:
- Lembah Subang
- Kelana Jaya
- Taman Bahagia
- Taman Paramount
- Asia Jaya
- Taman Jaya
- Universiti
- Kerinchi
- Abdullah Hukum
- Bangsar
- KL Sentral
- Pasar Seni
- Masjid Jamek
- Dang Wangi
- Kampung Baru
- KLCC
- Ampang Park
Disruption dates (stations open at 9am):
October: 11 (Sat), 12 (Sun), 18 (Sat), 19 (Sun)
November: 1 (Sat), 15 (Sat), 16 (Sun), 22 (Sat)
Stations not involved in the testing will operate as usual.
Commuter Support
- Free shuttle buses and vans will be available to connect affected stations.
- Station staff, auxiliary police, and Prasarana Troopers will be on-site to guide and assist passengers.
For more details and updates, visit www.myrapid.com.my or follow Rapid KL on social media.